ToolBase.org logo
The Home Building Industry's Technical Information Resource

Back to Standard View
Building SystemsHome Building TopicsDesign & Construction GuidesBest PracticesConstruction Methods
Adobe Acrobat Reader required for PDF documents

PDF documents require the free Adobe Reader.


All PDF documents open in a new browser window. Close the browser window to return to the site.

Shorten Build Time with Cell Teams

     

Tight scheduling demands that the trades complete their work on time. They must stay on schedule or face the wrath of their builder. Many builders have successfully used this method to cut weeks off of their build schedule.

The dark side of this scenario is that the trades add extra safety to complete their work. It doesn't take long for the trades to learn that the more safety time they can add, the more likely they are to beat the schedule. Even if they can beat the schedule, they will take the allotted time for fear that the extra time may be taken away.

A framer that averages five days will want a seven-day schedule because occasionally it takes that long. The foundation contractor adds two days for contingencies. Plumbing, electrical, and HVAC each add a day for possible problems. Before you know it, the single largest activity that appears scattered throughout the overall plan is safety time set aside for occasional delays. In our example, seven days of safety time were used to set a firm date for the pre-drywall inspection. The resulting cost is enormous. Using safety time more efficiently is an excellent opportunity for reducing overall build time.

Manufacturing industries have been reducing their cycle time by changing their scheduling methods. They recognize that scheduling a single group of as few as four combined activities has higher schedule reliability with half the total safety time.

EG&G Pressure Science, a Maryland aerospace parts manufacturer, used a computerized scheduling system to tightly schedule and control step by step production activities. After an initial reduction, cycle times stabilized at new levels. Wishing to reduce cycle time further they established cell teams, groups of craftsmen that work together, for each major phase of production. The cell teams manage their own internal production schedule. Now the computerized scheduling system controls only production between cells. Overall production cycle time was cut in half while scheduling was simplified by a factor of four.

Adapting this approach to builders, cell teams consisting of multiple trades can be organized for each phase of construction. Each trade in the cell is scheduled using the normal task time, without safety time. A single safety time is then scheduled at the end of the phase.

On at least half the jobs, each trade can be expected to meet or beat their scheduled duration. On the other jobs, the trades would need to be flexible enough to slide back when one of the previous trades experiences a delay. The scheduled completion time for the phase would stay on time because delays can be absorbed by the phase safety time.

Builders have been following manufacturing’s lead in the evolution of scheduling methods. Whether builders will continue to follow the same evolutionary path or jump ahead remains to be seen. Let's keep an eye on this one.