Location: |
Mobile, AL |
|
Climate Zone: |
2 Humid |
|
Subdivision: |
various |
Evaluation
Start Date: |
July 2008 |
|
Estimated Completion Date: |
July 2009 |
|
|
|
Objectives: |
- Measure costs and labor for several foundations widely used in the southern states surrounding the Gulf of Mexico
- A raised crawlspace (or stem wall) foundation with a wood floor deck
- A raised concrete slab foundation
- A slab-on-grade foundation
- Capture costs, labor and timing for each type of foundation and first floor system.
- Compare results.
- Provide information to make informed decisions regarding the types of foundation/floor systems available in the region and the approximate costs.
- Record and analyze the crawlspace conditions in two adjacent houses; one naturally vented and the other mechanically vented by a “smart” fan.
|
|
General Construction Information: |
Concrete masonry unit stem wall foundations with wood or concrete first floors will be featured in this cost study. |
|
Significant Results: |
Project start up July 2008. |
|