ToolBase Services
The Home Building Industry's Technical Information Resource

Back to Standard View
Search by Building SystemBrowse by Evaluated TechnologyAbout Field Evaluations

Weingarten House: Rappahannock County, VA

Summary
Details
Results
Journal
Resources

9/12/06: Home Occupied - Finishing Touches

Front North Elevation Stucco Finish Completed

Front North Elevation Stucco Finish Completed

Rear South Elevation

Rear South Elevation

Southwest Corner

Southwest Corner


9/12/06 continued

Northeast Corner

Northeast Corner

Living Room & Kitchen(Looking West)

Living Room & Kitchen(Looking West)

Kitchen & Front Hallway (Looking North from Kitchen)

Kitchen & Front Hallway (Looking North from Kitchen)


9/12/16 continued

Living Room (Looking East)

Living Room (Looking East)

Water Heater - Connections to Water Supply & Geothermal Heat Pumps

Water Heater - Connections to Water Supply & Geothermal Heat Pumps


6/8/06: Stucco Application & Interior Finishing

Northeast Corner Stucco Finish

Northeast Corner Stucco Finish

Southwest Corner

Southwest Corner


6/8/06 continued

West Kitchen Area

West Kitchen Area

Kitchen Area

Kitchen Area


3/8/06: Geothermal heat pump installed, house insulated

Geothermal heat pump was installed and is operating, and house has been insulated. Sensors were installed to measure interior temperature in several locations on first and second floors. The house was ready for drywall installation.

Geothermal Heat Pump was installed

Geothermal Heat Pump was installed

House was insulated

House was insulated


12/22/05: Download data logger

Temperature data from May-December was downloaded from the data logger, and is being analyzed. Walls are ready for stucco finish.

PEX Radiant Floor Heating and Cooling, and Plumbing Manifolds

PEX Radiant Floor Heating and Cooling, and Plumbing Manifolds

PEX Hot & Cold Water Supply and Plumbing Manifolds

PEX Hot & Cold Water Supply and Plumbing Manifolds

PEX Plumbing to Shower

PEX Plumbing to Shower


12/22/05 continued

Plumbing, electrical, and HVAC have been roughed in.

PEX Hot & Cold Water Supply and Manifolds, Terra Brick Exterior Wall

PEX Hot & Cold Water Supply and Manifolds, Terra Brick Exterior Wall

Rear (South) Elevation. Low-e Windows and Doors. Soy-based Foam Insulation and Stucco Mesh

Rear (South) Elevation. Low-e Windows and Doors. Soy-based Foam Insulation and Stucco Mesh

West Elevation. Large Overhangs, Soy-based Foam Insulation, Stucco Mesh, and Weather Station

West Elevation. Large Overhangs, Soy-based Foam Insulation, Stucco Mesh, and Weather Station


9/13/05:Windows, Doors, and Exterior

Windows and doors, and Exterior soy-based foam board insulation were installed.

French Doors and Windows in South Wall

French Doors and Windows in South Wall

Doors and Windows at Southwest Corner

Doors and Windows at Southwest Corner


9/13/05 continued

Northwest corner of home

Northwest corner of home

South side of home

South side of home


7/23/05:Temporary wiring

Owner will contact electric utility about stubbing out meter base to allow for insulation board. Note temporary wiring inside panel board.

Temporary wiring at panel

Temporary wiring at panel


7/22/05: Roof framing

For roof framing, hurricane clips were installed at the TJI rafter/kneewall bearing above North exterior wall.

Hurricane clips East end of North wall

Hurricane clips East end of North wall


7/15/05: Transformer installed

Electrical transformer is installed behind the house.

Electrical transformer behind house

Electrical transformer behind house


7/11/05: Wall construction

During wall construction, two inch soy-based polyurethane insulation board (see www.emegabuild.com) is installed on the North exterior wall and a portion of the East exterior wall. At this time the thermocouple wires were not in place on the outer surfaces of brick and insulation. Coordination will be needed to ensure proper placement of thermocouples on all four exterior walls, as well as access for thermocouple wires to the upstairs.


6/14/05: Electrical conduit installed

Electrical conduit for service entrance and meter base are installed outside the utility room. A 200A panel box is installed on the inside of the wall with a cable to a temporary outlet upstairs. No other wiring is installed at this time.

200 Amp Panel Box

200 Amp Panel Box

Meter base

Meter base


6/1/05: Soy-based foam insulation

Insulation was delivered to the site and is ready for installation.


5/1/05: Data logger download

Temperature data from January - May was downloaded from the datalogger and is being analyzed.


4/28/05: Roof sheathing continues

The roof sheathing continues and has now been completed on North side of home. Underlayment and roofing nails are on site. The thermocouple wires were reattached to the exterior side of the brick walls.

Sheathing completed north elevation

Sheathing completed north elevation


4/19/05: Roof sheathing begins

Construction resumes as roof sheathing is applied and thermocouple wires that were caulked to the exterior side of the brick walls need to be reattached.

Roof sheathing started North side

Roof sheathing started North side


4/2/05: Rain delays

Excessive rain delays construction.


3/31/05: Porchslabs poured

Porch slabs were dug and then poured for both the north and west sides of the home.

Front porch slab poured

Front porch slab poured

Side porch slab

Side porch slab


3/17/05: Thermocouples installed

Thermocouples were installed in exterior walls and connected to the datalogger. Second floor and roof framing was completed and weather station was set-up.

West elevation

West elevation


3/9/05: Roof framing and foundation insulation

Installation of roof framing and exterior wall insulation continues. The 12" rafters were reworked to bear on ledger at 2x6 kneewall. Framing and dormer rafters installed at East end. Installation of insulation around the exterior perimeter began.

Northeast elevation

Northeast elevation

Foundation insulation with 2" board

Foundation insulation with 2" board


3/4/05: Secondfloor and roof framing

Second floor and roof framing began, including microlam ridge beam with floor joist material bearing on perimeter kneewall. GreenGuard two-inch insulation board (R-10) is stacked on first floor to be used as floor slab insulation.

Beginning of roof framing

Beginning of roof framing


2/3/05: Lumber and materials delivered

There has been no progress in the construction of exterior walls since 01-19-05. Some additional material (rebar and lumber) was delivered.

Northeast corner

Northeast corner


1/19/05: Thermocouple readings downloaded

NAHB Research Center staff connects a laptop to the datalogger to download thermocouple readings (15 minute intervals) for 12-29-04 to 01-19-05. First course of TerraBrick walls have been grouted to floor slab. Subsequent courses have been dry-stacked to the top of window and door headers.

Downloading Datalogger

Downloading Datalogger

TerraBrick Wall NW Corner

TerraBrick Wall NW Corner


1/4/05: TerraBrick walls dry-stacked

Nearly half of the TerraBrick for the North wall has been dry-stacked. Portions of the East and West walls have been started.

Inside north wall

Inside north wall


12/29/04: Layout of walls

Layout for the first course of exterior wall begins. The home owner and designer spent most of the day reviewing plans and laying out the first course of TerraBrick. First corner bricks were then set in mortar. Eight inch lengths of rebar were cut for holes drilled through TerraBrick and into slab to provide lateral resistance near each end of exterior wall sections.

Northeast corner

Northeast corner

South Wall

South Wall


12/04: Slab and data logger installed

The slab was placed and foundations walls began. Sensors and a datalogger were installed in December to measure temperature at three layers, in and under the slab, and in the exterior air and subsoil.

Foundation walls

Foundation walls


9/04: Construction began

Construction began on energy efficiency package home with Terra Brick, Soy-Based Foamboard Insulation, Geothermal Heat Pump, Radiant Floor Heating and Cooling and Solar Water Heating. The designer John Spears, Institute for Building Technology and Safety (IBTS), and Jim Wilson of Wilson Engineering Services, will be monitoring the heating and cooling system and energy usage. Michael Vaughan of Portfolio Productions will document construction and installation of technologies.