Hughes Construction: Lexington, NC
October 2001
All buildings complete. Buildings are blower door and duct blaster tested.
|
September 2001
Electric meters and a weather station are installed.
|
August 2001
Baseline building complete. Mechanical equipment is being installed in the other three buildings
|
February 2001
Monitoring equipment installed in all buildings
|
January 2001
Building #2 walls and floor framed with light-gauge steel. Placement of the joists went very quickly. Installation of the floor deck was similar to installation with wood framing with the exception of using screws rather than nails.
AAC block laid by four-man crew with no previous AAC experience. A heavy-duty drill with an extended bit and 3 ½-inch hole bore and a crosscut hand saw were used to core and cut the blocks.
|
December 2000
Framing continues on first three buildings.
|
|